Printable Version [PDF/228 kb]
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
| 2010 | ||||||||||||
| Close 1 lane each direction Maryland Heights Expressway, River Valley to Page Ave. | X | |||||||||||
| Start sewer placement, Water Works Rd. South | X | |||||||||||
| Start pavement widening, River Valley to Water Works Rd. | X | |||||||||||
| Close 1 lane each direction Maryland Heights Expressway through Page ave. interchange | X | |||||||||||
| Start pile driving Bridge 286 | X | |||||||||||
| Start pile driving Bridge 287 | X | |||||||||||
| Start pile driving Bridge 288 | X | |||||||||||
| Start pile driving Bridge 289 | X | |||||||||||
| Start retaining walls at Water Works Rd. | X | |||||||||||
| 2011 | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
| Start retaining walls South | X | |||||||||||
| Start setting girders Bridge 287 | X | |||||||||||
| Start setting girders Bridge 288 | X | |||||||||||
| Close Maryland Heights Expressway at Water Works Road - detour on Creve Coeur Mill Rd. | X | |||||||||||
| Relocate Creve Coeur Mill Road North to Water Works Rd. | X | |||||||||||
| Start setting girders Bridge 289 | X | |||||||||||
| Start pavement from Water Works to South | X | |||||||||||
| Complete Bridge 287 | X | |||||||||||
| Start setting girders Bridge 286 | X | |||||||||||
| Complete pavement widening, River Valley to Water Works Rd. | X | |||||||||||
| Complete Bridge 288 | X | |||||||||||
| Complete Bridge 289 | X | |||||||||||
| Complete Bridge 286 | X | |||||||||||
| 2012 | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
| Place signage South | X | |||||||||||
| Start Landscaping | X | |||||||||||
| Complete pavement, Water Works South | X | |||||||||||
| Complete Project | X |