St. Louis County received $20 million in American Recovery and Reinvestment Act (ARRA) funds.
Autumn will see the completion of all four bridges on the project and major earthwork. Pavement pours will continue from Olive north to Waterworks Road. Tree planting will begin along the project corridor.
River Valley to Page Avenue
The majority of the new concrete pavement has been constructed. Traffic signal work is nearly complete.
Page Avenue Intersection
The circular ramp to westbound Page Avenue is complete. Mainline pavement modifications are nearly complete including shoulders.
Page to Water Works Road
Earthwork continues near the new bridge over the railroad tracks. Mainline concrete pavement pours in this area will continue over the next several weeks. Due to this ongoing operation, the current detour will stay in place.
Water Works Road to Olive Boulevard
The construction of the three remaining bridges is well underway and will be complete. Along with the upcoming bridge deck pours, earthwork grading and retaining wall construction will continue between the bridges.